Florida ADU law in 2026
Short answer: there is no statewide right to build an ADU in Florida. Cities and counties decide, lot by lot.
What state law says
Section 163.31771, Florida Statutes, permits local governments to allow accessory dwelling units. It does not require them to.
SB 48 (2026), which would have widened ADU rights, passed the Senate on February 4, 2026 and died in the House on March 13, 2026. Any claim of a statewide ADU right effective 2026 is wrong.
What that means for your lot
Whether you can build an ADU depends on the jurisdiction on the folio. Unincorporated Miami-Dade has an ADU program with a 7,500 sq ft minimum lot. The City of Miami and every other city set their own rules, or none.
What the state does set
- The Florida Building Code applies statewide. Miami-Dade and Broward are the High-Velocity Hurricane Zone, with product approvals and impact-rated openings.
- Modular buildings carry a state approval through DBPR's manufactured buildings program, but still need the local permit package: foundation and anchoring, site plan, energy calculation and MEP.
- Private-provider plan review and inspections are allowed under Florida Statute 553.791.
As of November 2026. A Lot Check answers the ADU question for one parcel, with the local section cited.
Questions
Does Florida allow ADUs statewide in 2026?
No. Florida has no statewide ADU mandate. Section 163.31771 lets local governments allow ADUs but does not require it; SB 48 died in the House on March 13, 2026.
Who decides if I can build an ADU in Florida?
Your city, or the county if the lot is unincorporated. Check the Municipality field on the property appraiser record.
Do modular ADUs need a local permit in Florida?
Yes. A state modular approval covers the unit; the foundation, site plan, energy calculation and MEP still go through the local permit.